Influence assessment of shut-in duration and well startup sequence in different geological and field conditions

Cover Page

Cite item

Full Text

Abstract

During 2019-2021, about half of well stock at West Siberian oil fields were shut down for a long period (up to one and a half year) due to oil production restrictions under the agreement between Russia and OPEC (Organization of the Petroleum Exporting Countries). There have never been such large-scale and prolonged shutdowns before. After starting from a long-term shutdown, the flow rate of some wells increased, while others decreased.The main aim of research is to assess the geological and technological factors affecting the results of starting wells after a long shutdown. Statistical methods were used, including multivariate regression analysis, assessing the influence of parameters on each other using trend lines on cross-plots, as well as constructing and comparing maps of geological and technological parameters.As a result, the influence of the duration of downtime, the simultaneity of shutdown of production and injection wells and compensation of production by injection was determined. That will help to reduce losses in case of repeated production restrictions by selecting optimal candidates for shutdown.

About the authors

A. V. Grezin

Ufa State Petroleum Technological University

Email: grezin_86@mail.ru

D. K. Sagitov

Ufa State Petroleum Technical University

References

  1. Reservoir Commentary : Potential Implications of Long-Term Shut-Ins on Reservoir. –doi: 10.2118/0720-0031-JPT. – Direct text // Journal of Petroleum Technology. – 2020. – Vol. 72, Issue 07. – Р. 31–33.
  2. Ровинский, М. В. Результаты остановки скважин объекта АВ1-2 Урьевского месторождения по ограничению ОПЕК / М. В. Ровинский, В. В. Реймер, Р. Р. Хафизов. – doi: 10.33285/0207-2351-2022-12(648)-58-62. – Текст : непосредственный // Нефтепромысловое дело. – 2022. – № 12 (648). – С. 58–62.
  3. Impact of Temporary Well Shut-Ins on Unconventional Reservoir Performance / T. Firincioglu, B. Basbug, M. Freeman. – Text : electronic // NITEC LLC Research White Paper. – 2020. – URL: http://www.nitecllc.com/wpcontent/uploads/2016/02/Impact-of-Temporary-Well-Shut-ins-on-UC-Reservoir-Performance_20200525.pdf.
  4. Дьячук, И. А. Анализ временной остановки эксплуатационных скважин на завершающей стадии разработки и приблизительная оценка скорости накопления остаточной нефти / И. А. Дьячук, Е. В. Князева, Н. С. Кутуков. – Текст : непосредственный // Георесурсы. – 2013. – № 4 (54). – С. 72–78.
  5. Jacobs, T. The Great Shale Shut-In Uncharted Territory for Technical Experts / T. Jacobs. – doi: 10.2118/0620-0024-JPT – Direct text // Journal of Petroleum Technology. – 2020. – Vol. 72, Issue 06. – P. 24–27.
  6. Янин, А. Н. Влияние простоев добывающих скважин на нефтеотдачу прерывистых пластов / А. Н. Янин, Р. А. Закирова. – Текст : непосредственный // Бурение и нефть. – 2010. – № 3. – С. 18–21.
  7. Савенков, В. Ю. Оценка влияния преждевременного выключения скважин на эффективность выработки запасов : специальность 25.00.17 «Разработка и эксплуатация нефтяных и газовых месторождений» : диссертация на соискание ученой степени кандидата технических наук / Савенков Виталий Юрьевич ; Российский государственный университет нефти и газа имени И. М. Губкина. – Москва, 2002. – 166 с. – Текст : непосредственный.
  8. Совершенствование методов оценки и планирования геологотехнических мероприятий на базе статистических данных / В. С. Никитин, С. Д. Глебов, Д. К. Сагитов, А. А. Махмутов. – Текст : непосредственный // Нефтепромысловое дело. – 2014. – № 12. – С. 26–29.

Supplementary files

Supplementary Files
Action
1. JATS XML

Согласие на обработку персональных данных

 

Используя сайт https://journals.rcsi.science, я (далее – «Пользователь» или «Субъект персональных данных») даю согласие на обработку персональных данных на этом сайте (текст Согласия) и на обработку персональных данных с помощью сервиса «Яндекс.Метрика» (текст Согласия).